Greenville Council approves $5.46M for City Hall renovation, United Community office deal
The 53-year-old headquarters on South Main Street will undergo a two-year overhaul, while the bank secures a spot in the new Falls Park Conference District.
By Maya Morris ·

Greenville City Council approved an ordinance on Nov. 23 to allocate $5.46 million from the city’s capital projects fund for the renovation of Greenville City Hall. The funding covers the mobilization and demolition phases of the project, as well as pre-construction planning and permitting services provided by Greenville-based DP3 Architects.
The 10-story office building at 206 S. Main St. was turned over to contractor Reeves Young in early November. The city’s 53-year-old headquarters will undergo extensive interior and exterior work, a process expected to take approximately two years to complete.
In a separate action, the council gave initial approval to a development agreement with United Community for the planned Falls Park Conference District. The city is purchasing 2.3 acres of property from the bank along Falls Street and Webster Street. The parcel sits across from United Community’s headquarters at 200 E. Camperdown Way.
Under the approved site plans, United Community will build a new Class A office structure above the district’s planned parking garage. This development forms part of the mixed-use district the city is developing in downtown Greenville.
The council also certified the Bowater Building at 55 E. Camperdown Way as an abandoned textile mill site under the South Carolina Textiles Communities Revitalization Act. Camperdown Mills originally operated the property as a textile manufacturing facility before Camperdown Company Inc. took over. Greenville-based Auro Hotels plans to spend $110 million converting the existing four-story office building into a 335-room JW Marriott hotel within the Falls Park Conference District. The state act provides income tax credits for the rehabilitation.
Final approval was given to a public infrastructure improvements agreement with Verdae Properties LLC. The Greenville-based developer will fund and build public infrastructure within the 92-acre Bolden Street District along Laurens Road. The city intends to buy back and maintain these resources by issuing bonds repaid with additional property tax revenues from the tax increment financing district established along the corridor in 2024.
Additional approvals included $976,000 in state funds for infrastructure in the Greenline-Spartanburg neighborhood and $650,000 in combined state and local funding to purchase the former Greenville Cultural Exchange Center at 700 Arlington Ave. The council also adopted the 2024 International Building Codes and approved a 3.4% cost-of-living adjustment for firefighters’ pension benefits.